| Planning Permission |
|
|
|
| Written by Administrator |
| Wednesday, 07 July 2004 12:00 |
|
Most conversions will not require planning consent – particularly those with roof windows to the rear only. Planning permission will always be required
* Applications should be made to the Local Authority and a decision must be given by them in eight weeks. Sometimes ‘Additional Information’ is sought and a further eight weeks from receipt of the necessary information is then allowed for the Local Authority decision. |
| Last Updated ( Monday, 30 March 2009 14:58 ) |